'Past wrongs and bad luck' meant giant UK offshore wind round still fell short

ANALYSIS | Government would have 'hoped for more' than 3.8GW of new offshore wind procured to give it fighting chance of meeting its 60GW by 2030 target, say industry experts

Almost half the auction's budget went on shoring up projects awarded contracts in 2022 or was not used at all due to "bad luck," said Leo Bertels, associate director at BVG Associates
Almost half the auction's budget went on shoring up projects awarded contracts in 2022 or was not used at all due to "bad luck," said Leo Bertels, associate director at BVG AssociatesPhoto: BVGA

The latest UK renewables auction was a welcome return to form for offshore wind but a need to “right past wrongs” and simple bad luck meant it fell short of what the government may have hoped for, pushing 2030 targets further out of reach, say analysts.

There had been huge pressure on this year’s contracts-for-difference (CfD) auction, known as AR6, to succeed after no offshore wind developers bid in last year’s calamitous edition due to the unsustainably low power price on offer.

A turbocharged administrative strike price (ASP) of £73/MWh ($96/MWh, at 2012 prices, equivalent to £105.78 now based on RPI inflation) and a record-smashing £1.1bn budget set for this year’s auction led to predictions that close to the 10GW of projects available to bid could win contracts.

A figure approaching that would have breathed new life into the new Labour government’s incredibly ambitious target of having 60GW of offshore wind, including 5GW of floating wind, up and running in UK waters by 2030, up from 15.5GW now.

In the event, only 3.4GW of new fixed-bottom offshore wind projects won CfD contracts – namely Orsted’s 2.4GW Hornsea 4 and ScottishPower’s 960MW East Anglia Two. A further 400MW was awarded to the floating Green Volt project.

Another 1.6GW of contracts went to projects that had come through the AR4 round in 2022 but – battered by economic headwinds – re-bid in this edition to get a better price for their power.

For ScottishPower CEO Keith Anderson, the results showed the offshore wind industry is “back on track.” But Tom Glover, UK head of RWE, which had several gigawatts of projects eligible to bid, lamented that the round “only procured around 35% of the total eligible pipeline.”

If the government wants to hit its 2030 target, Glover said it will need to significantly ramp up procurement,” calling for it to “urgently review and confirm the parameters for next year’s auction.”

AR4 projects eat into AR6 budget

“UK offshore wind is back, and that is something to be celebrated, but AR6’s focus has been diverted to some extent by righting the wrongs of previous rounds, rather than delivering new capacity,” Leo Bertels, associate director at BVG Associates, told Recharge.
AR4 was the boom before last year’s bust, with 7GW of offshore wind projects awarded contracts at £37.35/MWh. But those projects since contended with spiralling inflation, high commodity prices and supply chain pressures, resulting in Sweden’s Vattenfall pulling the plug on the 1.4GW Norfolk Boreas array (since sold to RWE) and its AR4 contract.
The government responded by allowing developers to re-bid up to 25% of projects previously awarded CfDs in this round to secure a more viable strike price, with an energy ministry spokesperson telling Recharge these projects “would have been lost otherwise.”

All the other projects that came through AR4 took up this offer, winning a new strike price of £54.23/MWh.

The ‘permitted reduction’ scheme, as it is known, was an “important insurance mechanism” to ensure that projects can keep progressing even when there are “external shocks,” such as the war in Ukraine, said Luke Clark, director of industrial growth at RenewableUK.

It did, however, eat up a £251m share of the AR6 budget, said Bertels. A further £230m of the budget, or 21%, went unspent, most likely due to the next cheapest project available being “too large to fit within the allocated pot budget.”

“This is probably more a case of bad luck than bad planning, but both industry and government would have preferred to see the budget fully utilised to drive forward as much deployment as possible.”

All in all, that means that only around 56% of the available budget was actually spent on new fixed-bottom projects.

‘Government would have hoped for better result’

The challenge to get to 55GW of fixed-bottom capacity by 2030 was already “incredibly ambitious,” said Sam Hollister, head of energy economics at LCP Delta.

“There is no doubt that to get nearer that landmark, the government would have been hoping for more offshore projects this time around,” he said, stressing there were still a record 131 renewables projects procured across the entire auction.

“Next year will be interesting, as we can expect to see some onshore wind projects in England coming forward given the recent lifting of the ban, and if there is a sizeable offshore wind budget, then we can certainly expect to see levels similar to AR4”.

Peter Lloyd Williams, senior analyst at Westwood Global Energy Group, said that AR6 was a “mixed bag for offshore wind.”

It is he said interesting that the top strike price for offshore wind in this round, £58.87/MWh, was “‘only’ 34% higher than the much-lamented strike price” in AR5 last year that resulted in a developer no-show.

It was also “someway below the maximum” of £73/MWh, “which only serves to highlight the extent to which AR5 was a lost opportunity.”

That “19% discount” on the ASP “highlights the competitiveness of the auction round, with high levels of participation from developers,” said Aurora Energy analyst Pranav Menon.

“This was largely expected, given the large pipeline of projects eligible to participate in the auction round and the high ASP, which offered lucrative returns.”

“Ultimately, such competitive price discovery is exactly what you like to see in a CfD auction, as it ensures that low-carbon capacity is delivered while also minimising the cost to consumers.”

‘Reforms needed’ to auction design

Menon believes it is now "highly unlikely" the 2030 target will be met, with analysts estimating the government is only around halfway to procuring the 60GW of capacity it is targeting through its CfD process.

Challenges go "beyond just financing," he said, with "stretched supply chains and limited port infrastructure" other key limitations.

Signe Tellier Christensen, an analyst for Aegir Insights, added: "While this round succeeded in terms of multiple gigawatts awarded... this is not a sufficient result to be on track for the UK government’s 2030 target. Of the 4.9GW fixed-bottom projects awarded, around 30% of the capacity were projects rebidding. So, the UK still has a back-log of shovel ready projects waiting on offtake."

Frankie Mayo, UK policy chief at climate think tank Ember, believes government targets “remain in sight, especially as many CfD upgrades are being discussed such as big budgets or more regular auctions.”

According to target commissioning data, he said the projects from this round hope to come online in 2028 and 2029, meaning that “potentially the next two auctions” could support projects for delivery by 2030.

He argued however that “larger reforms” are needed, with the competitive CfD structure meaning the UK is “struggling to achieve the scale required”.

Instead of encouraging developers to bid against each other for a limited pot of money, he said the government should outline a reasonable price for power and “encourage as many projects as possible” to come forward and apply, “rather than creating losers through the current bidding process.”

(Copyright)
Published 4 September 2024, 09:47Updated 4 September 2024, 10:43
UKEuropeIberdrolaScottishPower RenewablesOrsted