Virginia approves largest US offshore wind array despite final cost concerns

State utilities regulator approves Dominion Energy's 2.6GW plan following suspension last summer over 'unfeasible' performance guarantees

Dominion Energy's CVOW pilot project off Virginia.
Dominion Energy's CVOW pilot project off Virginia.Foto: Dominion

The US’ largest offshore wind project, a 2.6GW behemoth off the coast of Virginia, was greenlighted by the state utilities regulator following a dispute over performance guarantees and despite concerns regarding final costs.

The State Corporation Commission (SCC) approved utility Dominion Energy’s $9.8bn Coastal Virginia Offshore Wind (CVOW) project despite forecasts that it is “likely the costliest project being undertaken by any regulated utility in the US”.

It also noted that electricity the project will generate “will be among the most expensive sources of power”.

In its final order, SCC estimated total projects costs, including financing, less investment tax credits, could balloon to $21.5bn.

Virginia’s tightly regulated market enables Dominion to develop CVOW as if it were a conventional power project, which includes guaranteed returns on investment contingent on SCC approval.

SCC and stakeholders including Walmart, consumer advocacy group Appalachian Voices, and Sierra Club, raised concerns regarding possible cost overruns and sought performance guarantees to ensure that consumers would not be paying for an underperforming asset.

Dominion rejected these performance guarantees as “unfeasible” and sought their elimination, resulting in initial suspension of final SCC approval.

The utility later tabled a compromise that would see it take 50% of responsibility for overruns on the original capital investment (capex) from $10.3bn-$11.3bn and accept the full share should costs reach $11.3bn-$13.7bn.

“All parties at the hearing either assert that the Second Stipulation [Dominion’s compromise] adequately protects the interests of consumers or have no opposition to the Commission's approval thereof,” the SCC said. “Accordingly, it is so ordered, the Final Order is no longer suspended.”

“We thank the Commission for its approval and appreciate the collaboration of the parties involved to reach an agreement that advances offshore wind and the clean energy transition in Virginia,” Jeremy Slayton, Dominion Energy spokesman, told Recharge.

With the state approval in hand, the project now only has to gain consent of the federal government.

The Bureau of Ocean Energy Management (BOEM), the regulator of energy development in federal waters, issued CVOW its draft environmental impact statement (EIS), setting the stage for final approval as early as next summer.
The EIS is an assessment by multiple federal agencies of each project's construction and operations plan to determine its impact on the local and regional environment. Release of the draft EIS is slated for 16 December publication in the Federal Register, the US government journal of record, opening a 60-day public comment period.

CVOW is the only offshore wind array owned exclusively by a US utility.

Some $6.9bn in supplier contracts have been signed by Dominion for the project, sparking a boom in investment into Virginia’s Portsmouth Marine Terminal (PMT). This includes a $200m blade finishing plant pledged by OEM Siemens Gamesa upon finalising the sale of 176 of its 14MW SG14.0 222 DD turbines.
PMT is undergoing a $223m upgrade to serve as both marshalling and manufacturing port for the offshore wind industry.
(Copyright)
Published 15 December 2022, 23:14Updated 16 December 2022, 13:42
AmericasUSVirginiaDominion EnergyCVOW