Why flagship Subsea 7 vessel will play a limited role at giant Dogger Bank offshore wind
Installation of foundations has remained ahead of schedule at world's largest project despite shipyard 'crane incident' that set back delivery of Alfa Lift
The semi-submersible heavy installation vessel will join Subsea 7's fleet in the third quarter of 2023.
It was built at China Merchants Heavy Industry (CMHI) shipyard in Jiangsu, China and was originally earmarked to carry out foundation installation operations on SSE’s flagship Dogger Bank wind farm.
In its earnings update at the end of July, Subsea 7 reported that 71 of Dogger Bank A’s 95 monopiles have been installed and that it was “on track” to complete this scope in the third quarter of 2023, and finish the transition pieces in the fourth quarter, ahead of the original schedule.
Last week SSE reported that work to install the first wind turbine at the UK’s Dogger Bank – on course to be the world’s largest offshore wind farm – was set to begin "within days."
Dogger Bank will when fully built-out at a cost of some £11bn ($14bn) have a capacity of 3.6GW and supply, making the project a new benchmark in the ambition of the global offshore wind sector.
The vessel set sail from China last month and remaining mission equipment will be completed and commissioned Europe, according to the vessel’s designer Ulstein.
Bigger, better... but not yet
“A strong performance on Dogger Bank A will allow commencement on Dogger Bank B, and we expect to start installing monopiles in the third quarter of this year. The remainder will be installed in 2024 as planned," Evans said.
"The mission equipment for Seaway Alfa Lift remains under construction but is now removed from the critical path," Evans said, describing the move as a strategy to "derisk" Dogger Bank.
Stuart Fitzgerald, CEO of Seaway 7 added: ""We would not intend to install that mission equipment ahead of.. the 2024 campaign. We focused the vessel on transition pieces, and we see acceptable returns on the vessel investment in that mode, given these transition pieces are large and it is relatively high spec work."
Financing vessels
Subsea 7 also said it was in the process of concluding a $450m debt funding exercise to help conclude the construction and commissioning of the Seaway Alfa Lift and the Seaway Ventus heavy-duty jack-up vessel suitable for turbine and monopile installation, which is due for delivery at the end of 2023.
The Ventus is booked to carry out wind turbine installations on Germany’s Borkum Riffgrun 3 and Gode Wind 3 wind farm projects in 2024 and on monopile installations on the UK’s East Anglia 3 project in 2025.
(Copyright)